PGI receives $6M Order

PGI receives a $6M order from ETA for the installation of Fuel Gas Skids for the Aweer Station H, Phase III Project.

Scope of work included installation of the fuel gas system package manufactured by PGI under a separate supply contract, installation and testing of all interconnecting piping, installation and testing of 8 off Atlas Copco Fuel Gas Compressors, Installation of 8 off Steel Buildings, Installation and testing of all cabling, pre-commissioning and commissioning of the complete gas station.


Posted on Saturday, September 01, 2007