Mukhaizna Water Treatment Units Commissioned

Process Group International recently delivered 4 Induced Gas Flotation (IGF) Packages to Occidental for their Mukhaizna Central Processing Facility, located in southern Oman. The IGF Packages were designed and fabricated at the Abu Dhabi facility, and shipped to site by road. 

The Mukhaizna Central Production facility is producing around 50,000 Barrel/Day of oil. The resulting water production is being treated by 2 of the IGF Units, which were recently commissioned. The remaining 2 IGF Units are expected to be commissioned in coming weeks as water production increases further and installation of these packages in completed.

Each IGF packages has a design capacity of around 95,000 BWPD, with a total capacity for all 4 IGF Units of around 380,000 BWPD.


Posted on Sunday, July 12, 2009